Town officials vs. the actual facts

7 Woodbridge myths

Town officials have made a number of claims about the $118.5 million Beecher Road School plan. Here is what the record actually shows — with links to all available sources.

  1. Current facility does not support educational excellence

    Beecher is ranked #24 in CT by U.S. News & World Report out of 854 CT schools

    Check the source
  2. The school is falling apart

    March 2026 project consultant’s facility report: “the building, infrastructure, and site are typically in good condition”

    Check the source
  3. Beecher needs additional space for grades K-6

    Current enrollment is below the Town’s Nov. 2024 projections for K-6; existing space can be reconfigured at far less cost

    Check the source
  4. A six classroom Pre-K expansion is needed

    The Town provides no evidence that this expansion is needed or will be used, and no cost estimate to operate

    No evidence provided by Town
  5. Town officials say all options were considered

    The Town never considered Better Value proposals, including one by architect David Barkin, former Woodbridge BOE vice-chairman

    Check the source
  6. Advocates claim Beecher can obtain an extra 20% reimbursement for enrollment growth as per July 2026 new state law

    That state law requires at least 20% growth in the previous ten years: Since 2016, Woodbridge had only 11% growth (9% short of the requirement)

    Check the source
  7. Town officials promise maximum cost to taxpayers is $55.4 million

    The referendum’s legally binding Explanatory Text states that up to $118.5 million will be authorized for just this one project

    Check the source